For battery energy storage system (BESS) developers, securing equipment and site control is only part of the development equation. A project must also connect to the electric grid, and increasingly, BESS interconnection is one of the biggest sources of schedule, cost, and contractual risk.
This article is Part 3 of our Battery Storage Legal Roadmap Series. If you missed them, start with Part 1: Utility-Scale Battery Storage Projects: A Legal Roadmap for Developers, Property Owners and Other Stakeholders and Part 2: Before You Buy: Managing Real Estate and Permitting Risk for BESS Projects in New York and New Jersey. See all articles in the series here.
BESS interconnection is a growing challenge as data centers and other large-load customers seek to bring new facilities online on increasingly aggressive schedules. A BESS provider may ordinarily quote a project lead time of approximately 12 months, while a data center customer may request delivery and operation within six months. The problem is that equipment availability is only one component of the schedule.
Utility review, interconnection studies, land use approvals, construction permits, equipment procurement, utility upgrades, inspections, and commissioning can all affect the commercial operation date. For developers, property owners, contractors, and customers, the key is to address those dependencies before aggressive project milestones become binding contractual obligations.
A BESS project can both withdraw electricity from and inject electricity into the grid. Depending on the project’s size, configuration, location, and point of interconnection, the utility or regional transmission organization may need to study the project’s effect on the surrounding electric system and determine whether upgrades are necessary.
The applicable process also varies significantly by project. In New York, for example, the state’s Standardized Interconnection Requirements apply to distributed generation and energy storage systems of 5 MW or less that operate in parallel with utility distribution systems. Larger projects may implicate NYISO procedures. In New Jersey, transmission-level projects generally operate within the PJM framework, while distribution-connected projects may involve the applicable electric distribution company and state requirements.
These processes can’t be safely treated as administrative items to address after equipment is ordered or a construction schedule is established. The point of interconnection can affect project economics, engineering, required upgrades, and ultimately whether the proposed schedule is achievable.
Federal and regional regulators have been working to address longstanding interconnection delays. FERC Order No. 2023 required transmission providers to implement significant reforms, including a shift toward a “first-ready, first-served” cluster study process and stronger financial and site-control requirements intended to move viable projects through the queue more efficiently.
PJM has similarly restructured its interconnection process. As of September 2026, PJM reported that 617 projects representing nearly 169 GW remained in Phase 1 of its first new study Cycle. PJM says the reformed process is designed to take about one to two years, depending on each project’s impacts.
That timeframe illustrates the disconnect that can arise when a customer approaches a BESS project expecting commercial operation within six months. Even when a battery supplier can manufacture and deliver the equipment within the requested period, the BESS interconnection process may operate on a very different timeline.
Importantly, interconnection is not the only potential bottleneck. PJM has acknowledged that projects that have completed interconnection may still face permitting and supply-chain delays before reaching construction and operation.
One of the most common project-development risks is treating permitting, interconnection, procurement, and construction as separate workstreams without identifying how they depend on one another.
A customer may assume that if equipment can be delivered in six months, the system can be operational in six months. In practice, the developer may need local land-use approvals, building and electrical permits, fire-code review, environmental approvals, utility approvals, and potentially utility infrastructure upgrades before the system can be energized.
The sequencing matters. A project team should identify early which activities can proceed concurrently and which depend on completion of another step. It should also determine whether permits or approvals require a substantially final design and whether interconnection-study changes could force revisions to previously submitted plans.
This is particularly important for projects supporting data centers. The pressure to obtain power quickly is now attracting federal regulatory attention. In June 2026, FERC initiated proceedings involving all six regional grid operators under its jurisdiction, directing them to justify or reform their existing rules governing how large loads, including data centers and manufacturing facilities, connect to the electric grid.
Schedule is only half of the BESS interconnection equation. Cost can be equally significant. An interconnection study may identify network or system upgrades necessary to accommodate a project. Depending on the applicable tariff and project structure, the developer may bear responsibility for some or all of those costs. Changes in the point of interconnection, project capacity, charging profile, or equipment configuration can also affect the analysis.
Developers should therefore be cautious about committing to fixed project economics before understanding the likely interconnection requirements. Agreements should address who bears responsibility for utility upgrade costs, what happens if those costs exceed assumptions, and whether either party has termination or renegotiation rights if interconnection becomes economically impractical.
Early technical diligence can help. For example, PJM provides a Queue Scope screening tool that lets prospective interconnection customers evaluate potential generator locations before formally entering the interconnection process. Although screening can’t eliminate interconnection risk, evaluating grid conditions and potential points of interconnection before making major commercial commitments can reduce avoidable surprises.
Schedule risk becomes especially consequential when contracts across the project supply chain include liquidated damages provisions.
A data center owner may require its BESS provider to meet a specific commercial operation date, with liquidated damages accruing for delay. The BESS provider may impose similar obligations on its equipment supplier, EPC contractor, electrical contractor, or other vendors. Those parties may, in turn, impose schedule requirements on their subcontractors.
The result is a chain of contractual obligations built around a date that may depend partly on utilities, permitting authorities, or other third parties outside the contracting parties’ direct control.
Contracting parties should allocate that risk expressly rather than leave it to interpretation after a deadline is missed. Contracts should distinguish between delays within a contractor’s control and delays caused by utility studies, interconnection approvals, government permitting, required grid upgrades, or changes imposed by authorities having jurisdiction. They should also address notice requirements, extensions of time, force majeure where applicable, owner-caused delays, change orders, and the circumstances under which liquidated damages may or may not accrue.
Pay particular attention to whether obligations align throughout the contracting chain. A developer that accepts broad liquidated damages exposure from the customer but receives only limited schedule protection from its suppliers may retain a substantial gap in risk.
For projects under significant time pressure, the better approach is to develop the schedule backward from the required commercial operation date and identify every regulatory, utility, procurement, and construction milestone necessary to reach it.
Before committing to a six-, nine-, or twelve-month completion date, project participants should understand the BESS interconnection pathway, permitting requirements, equipment lead times, utility construction obligations, commissioning requirements, and realistic contingencies. Where uncertainty remains, the contract should reflect it.
This does not mean aggressive BESS schedules are impossible. It means the commercial agreement should not assume that equipment availability equals project availability.
BESS projects require coordination among developers, utilities, equipment suppliers, contractors, property owners, regulators, and local permitting authorities. Scarinci Hollenbeck’s Commercial Real Estate & Land Use attorneys can assist clients in New Jersey and New York with site diligence, permitting and land use issues, BESS interconnection and utility agreements, EPC and equipment contracts, schedule and liquidated damages provisions, and other project-development matters. Addressing these issues early in a project can help identify grid, cost, and schedule risks before they become disputes or threaten a project’s commercial operation date. To discuss a BESS project, contact Nicholas R. Wall or another member of the firm’s Commercial Real Estate & Land Use team.
No Aspect of the advertisement has been approved by the Supreme Court. Results may vary depending on your particular facts and legal circumstances.

For battery energy storage system (BESS) developers, securing equipment and site control is only part of the development equation. A project must also connect to the electric grid, and increasingly, BESS interconnection is one of the biggest sources of schedule, cost, and contractual risk. Key Takeaways This article is Part 3 of our Battery Storage […]
Author: Nicholas Wall

Director and officer liability increases sharply when a company is in financial distress. Decisions that would draw little attention in a healthy business can later be challenged by creditors, shareholders, bankruptcy trustees, and regulators as breaches of fiduciary duty, fraudulent transfers, or oversight failures. Understanding where that exposure comes from, and how to manage it, […]
Author: Michael Mietlicki

For developers pursuing battery energy storage system (BESS) projects, finding the right property is only the beginning. BESS site selection is as much a legal and transactional exercise as a real estate decision, with risk analysis central to the project’s ultimate success. Key Takeaways The core questions for BESS site selection in New York and […]
Author: Nicholas Wall

What should you expect when meeting a litigation attorney about a business dispute? You should expect to describe the dispute in your own words, hand over the most important documents, flag any deadlines or immediate threats, and leave with a clearer picture of the problem, what information is still needed, and the likely next steps. […]
Author: Michael Mietlicki

Arbitration resolves disputes privately before an arbitrator whose decision is usually final, while litigation resolves them in court with full rights of appeal. Whether a business ends up in arbitration or litigation is often decided when it signs the contract, long before any dispute arises. Key Takeaways When facing a contract dispute, carefully consider your […]
Author: Graham Staton

Can you own part of a business in New Jersey without a written agreement? Yes, it is possible. Under New Jersey’s Uniform Partnership Act, a partnership can arise when two or more people carry on a business as co-owners for profit, whether or not they ever intended to form one. Ownership doesn’t necessarily depend on […]
Author: Michael Mietlicki
No Aspect of the advertisement has been approved by the Supreme Court. Results may vary depending on your particular facts and legal circumstances.
Consider subscribing to our Firm Insights mailing list by clicking the button below so you can keep up to date with the firm`s latest articles covering various legal topics.
Stay informed and inspired with the latest updates, insights, and events from Scarinci Hollenbeck. Our resource library provides valuable content across a range of categories to keep you connected and ahead of the curve.
Let`s get in touch!
Sign up to get the latest from the Scarinci Hollenbeck, LLC attorneys!